RESOURCES · ENERGY INFRASTRUCTURE EXECUTION
Tools for taking
projects into the real world.
Frameworks, datasets and operational tools for reading the stretch that separates an energy pipeline from capacity that is genuinely available.
CORE FRAMEWORK · v1.0
PT Energy Execution Gap
It does not measure how many MW are announced. It organises the data so that it is possible to see where those MW sit along the path to operation and, when the data allow it, how long they take to move from one stage to the next.
Requested MW
Grid-defined MW
Permitted MW
Ready-to-build MW
Under-construction MW
Operating MW
BASELINE DATASET · 2024–2025
The first verifiable snapshot
These figures do not form a single conversion rate: they belong to different perimeters and stages. They are the public baseline from which consistent time series can be built.
| Perimeter | Stage / indicator | Value | Date | Source |
|---|---|---|---|---|
| RES · National Transmission Grid (RTN) | Connection requests | 348 GW | 31 Dec 2024 | Terna Development Plan 2025 |
| Solar + wind | Operating / installed | 57 GW | 31 Dec 2025 | Terna |
| Stand-alone BESS | Requests | ~253 GW | 31 Dec 2024 | Terna Development Plan 2025 |
| Stand-alone BESS | STMG accepted (grid connection solution) | 107.04 GW | 31 Dec 2024 | Terna Development Plan 2025 |
| Stand-alone BESS | Design in progress | 37.79 GW | 31 Dec 2024 | Terna Development Plan 2025 |
| Stand-alone BESS | Projects with clearance (nulla osta) | 11.57 GW | 31 Dec 2024 | Terna Development Plan 2025 |
| Stand-alone BESS | STMD / contract | 2.68 GW | 31 Dec 2024 | Terna Development Plan 2025 |
Methodological note: Terna’s connection-process categories do not automatically coincide with all six PT stages. Mapping is carried out only when the definition is sufficiently compatible; otherwise the figure remains classified according to the original source.
RESEARCH RELEASE · v2.0 · 23 SEPTEMBER 2026
23 BESS projects. 2.33 GW. A first measure of authorisation time.
The first verified project-level cohort comprises 23 stand-alone BESS projects totalling 2,334.53 MW. For each project, the date of the Single Authorisation (Autorizzazione Unica) application and the date of the decree have been verified against official acts.
days · median
days · mean
days · minimum
days · maximum
What it measures: calendar time between the AU application date reported in the official act and the Single Authorisation decree. What it does not measure: Requested→Permitted, connection lead time, Ready-to-Build, construction, or Permitted→Operating. The sample is documentary and is not representative of the entire Italian BESS universe.
Observed distribution: 6 projects under 15 months; 11 between 15 and 24 months; 5 between 24 and 36 months; 1 over 36 months. The Troia case includes a significant design variation: it is kept in the dataset but flagged as not fully comparable.
DATA MODEL
How the longitudinal dataset will be built
Every observation must retain: the date of the reading, technology, geographic area, grid perimeter, the source’s original stage, any associated PT stage, MW, the primary source, the project identifier when available, and the confidence level of the mapping.
No ratio between different stocks will be published as a “conversion rate”. Conversion requires the same cohort of projects observed over time.
This allows the framework to be updated without rewriting the rules when new data arrive.
Execution Beats Planning
The project management handbook for energy and infrastructure projects. From contract to commissioning.
Discover →BESS Guide 2026
Technology, permitting, connection, procurement, site works and commissioning.
Open →PT Prevention Radar™
Weak signals, deviations and precursor conditions, before they become events.
Discover →HSE Toolkit™
Safety Walk, Near Miss, Audit, Toolbox Talk and KPIs in a single operational control system.
Open →