Resources

RESOURCES · ENERGY INFRASTRUCTURE EXECUTION

Tools for taking
projects into the real world.

Frameworks, datasets and operational tools for reading the stretch that separates an energy pipeline from capacity that is genuinely available.

CORE FRAMEWORK · v1.0

PT Energy Execution Gap

It does not measure how many MW are announced. It organises the data so that it is possible to see where those MW sit along the path to operation and, when the data allow it, how long they take to move from one stage to the next.

01
Requested MW
02
Grid-defined MW
03
Permitted MW
04
Ready-to-build MW
05
Under-construction MW
06
Operating MW

Full methodology and manifesto →

BASELINE DATASET · 2024–2025

The first verifiable snapshot

These figures do not form a single conversion rate: they belong to different perimeters and stages. They are the public baseline from which consistent time series can be built.

PerimeterStage / indicatorValueDateSource
RES · National Transmission Grid (RTN)Connection requests348 GW31 Dec 2024Terna Development Plan 2025
Solar + windOperating / installed57 GW31 Dec 2025Terna
Stand-alone BESSRequests~253 GW31 Dec 2024Terna Development Plan 2025
Stand-alone BESSSTMG accepted (grid connection solution)107.04 GW31 Dec 2024Terna Development Plan 2025
Stand-alone BESSDesign in progress37.79 GW31 Dec 2024Terna Development Plan 2025
Stand-alone BESSProjects with clearance (nulla osta)11.57 GW31 Dec 2024Terna Development Plan 2025
Stand-alone BESSSTMD / contract2.68 GW31 Dec 2024Terna Development Plan 2025

Methodological note: Terna’s connection-process categories do not automatically coincide with all six PT stages. Mapping is carried out only when the definition is sufficiently compatible; otherwise the figure remains classified according to the original source.

RESEARCH RELEASE · v2.0 · 23 SEPTEMBER 2026

23 BESS projects. 2.33 GW. A first measure of authorisation time.

The first verified project-level cohort comprises 23 stand-alone BESS projects totalling 2,334.53 MW. For each project, the date of the Single Authorisation (Autorizzazione Unica) application and the date of the decree have been verified against official acts.

534
days · median
660
days · mean
371
days · minimum
1,506
days · maximum

What it measures: calendar time between the AU application date reported in the official act and the Single Authorisation decree. What it does not measure: Requested→Permitted, connection lead time, Ready-to-Build, construction, or Permitted→Operating. The sample is documentary and is not representative of the entire Italian BESS universe.

Observed distribution: 6 projects under 15 months; 11 between 15 and 24 months; 5 between 24 and 36 months; 1 over 36 months. The Troia case includes a significant design variation: it is kept in the dataset but flagged as not fully comparable.

DATA MODEL

How the longitudinal dataset will be built

Every observation must retain: the date of the reading, technology, geographic area, grid perimeter, the source’s original stage, any associated PT stage, MW, the primary source, the project identifier when available, and the confidence level of the mapping.

No ratio between different stocks will be published as a “conversion rate”. Conversion requires the same cohort of projects observed over time.

This allows the framework to be updated without rewriting the rules when new data arrive.

PROJECT EXECUTION

Execution Beats Planning

The project management handbook for energy and infrastructure projects. From contract to commissioning.

Discover →
BESS

BESS Guide 2026

Technology, permitting, connection, procurement, site works and commissioning.

Open →
PREVENTION

PT Prevention Radar™

Weak signals, deviations and precursor conditions, before they become events.

Discover →
HSE CONTROL

HSE Toolkit™

Safety Walk, Near Miss, Audit, Toolbox Talk and KPIs in a single operational control system.