PT Energy Execution Gap | Observatory

PT Energy Execution Gap

Pantaleone Turco’s observatory on the execution of energy infrastructure.

2026 pilot report

Report in preparation. The observatory’s methodology is already available on this page.

The first edition will distinguish connection requests, authorisations, readiness for construction, construction and operation. It will not directly compare data-centre requests with new renewable capacity.

Methodology

States S0–S6, homogeneous cohorts, sources and explicit limits. Sources: Terna Econnextion, Terna monthly reports and GSE.

How to read the report

Connection requests describe project interest, not production or consumption capacity that is already in operation. To avoid misinterpretation, figures are always distinguished by technology, date of the reading, capacity and status of the procedure.

Stages observed

  • S0: connection request.
  • S1: connection solution accepted.
  • S2: authorisation obtained.
  • S3: documented conditions for the start of construction.
  • S4: works started.
  • S5: energisation and commissioning.
  • S6: entry into operation.

Limits and revisions

Growth in a pipeline does not prove that the same projects have passed through the later stages. Conversion indicators require consistent identifiers and cohorts that can be traced over time. Projects still under way are not automatically classified as failures. Aggregated data do not allow delays to be attributed to a single factor without further evidence.

Further reading

From Permitted MW to Operating MW · Publications and tools · Author profile.

Author

Pantaleone Turco, International Project Manager & HSE Specialist.